1.2
1 1.2.1 Software Process Infrastructure in place DUE 07-Jul-02
Description The LCG project requires an agreed software process and appropriate support tools, including
repository, configuration and release management tools. The components of the infrastructure
are to be defined by an RTAG created for this purpose.
Metric Agreed services are up and running by due date
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
2 1.2.2 Prototype Hybrid Datastore completed DUE 08-Sep-02
Description First version of hybrid eventstore released. Limited functionality only required and expected to
be used by experts only.
 
Metric Functionality, interfaces and documentation delivered according to requirements set at June
persistency workshop.
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
3 1.2.3 LCG-1 Applications Environment Defined DUE 03-Nov-02
Description Each LHC experiment has a distinct application environment and other environment components
have been produced by IT. A common set must be selected to serve as the base for development
and for testing on the LCG prototypes
Metric Report from PEB by due date
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
4 1.2.4 LCG-1 Applications Environment Software Available DUE 05-Jan-03
Description Once the different components of the application environment have been defined, they must be
collected and made available centrally.
 
Metric software components identified in 1.1.3 available if software repository of 1.1.1
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
5 1.2.5 General Release Hybrid Event Store DUE 01-Jun-03
Description A more functional and robust (but not yet complete) version of the persistency framework.
This will be a release offering basic hybrid persistency services, properly documented and
packaged for general use by the experiments.
Metric Release made by due date.
LHC experiments able to make use of it.
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
6 1.2.6 Future Milestones DUE 01-Jun-03
Description Milestones for the remainder of the LCG project are yet to be defined
 
 
Metric Milestones defined
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J