1.5
1 1.5.1 Complete Specification of LCG-1 DUE 24-Nov-02
Description Agreement is reached on the level of resources required for LCG-1 and how these are to be
distributed across at least 5 sites in 3 continents.
 
Metric Specification available
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
2 1.5.2 Institutes Fabric Ready to Install DUE 02-Feb-03
Description Acquisition and installation of agreed hardware.
 
 
Metric The institutes identified in 1.4.1 have completed the acquisition and installation of the agreed
hardware.
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
3 1.5.3 Certification Started DUE 16-Feb-03
Description  
Installation of agreed middleware (1.3.1) on hardware of 1.4.2.
 
Metric Certification Started
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
4 1.5.4 Certification and LCG-1 Build and Delivery complete DUE 04-May-03
Description  
All the agreed hardware and software is up and running at each individual LCG-1 site.
 
Metric Certification and LCG-1 Build and Delivery complete
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
5 1.5.5 Commissioning Started DUE 04-May-03
Description This is the start of the process to bring the different sites together to form a coherent LCG-1.
 
 
Metric Commissioning Started
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
6 1.5.6 Commissioning Completed DUE 01-Jun-03
Description  
 
 
Metric The application software of 1.1.3 runs successfully on the LCG-1 service.
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
7 1.5.7 Future Milestones DUE 01-Jun-03
Description Milestones for the remainder of the LCG project are yet to be defined
 
 
Metric Milestones defined
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J