2.2
1 2.2.1 Deliver WP2 Effort DUE on going
Description Deliver WP2 effort as contracted
 
Primarily a UK responsibility
Metric Man months deviation from plan
 
 Current Total 1        
Current Threshold 1        
Status In Progress Status Date 05-Jun-02     J
2 2.2.2 Technology Assessment DUE 30-Apr-01
Description D2.1 Report of current technology
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
3 2.2.3 Requirements & Architecture DUE 30-Jun-01
Description D2.2 Detailed report on requirements, architectural design, and evaluation criteria
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
4 2.2.4 First Project Release DUE 30-Sep-01
Description D2.3 Components and documentation for the first Project Release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
5 2.2.5 Second Project release DUE 30-Sep-02
Description D2.4 Components and documentation for the second Project Release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status In Progress Status Date 05-Jun-02     J
6 2.2.6 Final Project Release DUE 30-Sep-03
Description D2.5 Components and documentation for the final Project Release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Not started Status Date 05-Jun-02     J
7 2.2.7 Evaluation DUE 31-Dec-03
Description D2.6 Final evaluation report
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on successful delivery of project releases    
Dependency      
Status Not started Status Date 05-Jun-02     J