2.6
1 2.6.1 Deliver WP6 Effort DUE on going
Description Deliver WP6 effort as contracted
 
Primarily a UK responsibility
Metric Man months deviation from plan
 
 Current Total 1        
Current Threshold 1        
Status In Progress Status Date 05-Jun-02     J
2 2.6.2 Integration & Operation DUE 30-Apr-01
Description D6.1 Testbed software integration process, operational policies and procedures report
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
3 2.6.3 Policies, evaluation and procedures DUE 30-Jun-01
Description D6.2 Project release policy, definitions, evaluation targets and procedures
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
4 2.6.4 First project release DUE 30-Sep-01
Description D6.3 First project release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on first project release deliverables from middleware workpackages    
Dependency      
Status Complete Status Date 05-Jun-02     J
5 2.6.5 First project release evaluation DUE 31-Dec-01
Description D6.4 Evaluation of testbed operation
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on successful deployment of first project release    
Dependency      
Status Complete Status Date 05-Jun-02     J
6 2.6.6 Second project release DUE 30-Sep-02
Description D6.5 Second project release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on second project release deliverables from middleware workpackages    
Dependency      
Status In Progress Status Date 05-Jun-02     J
7 2.6.7 Second project release evaluation DUE 31-Dec-02
Description D6.6 Evaluation of testbed operation
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on successful deployment of second project release    
Dependency      
Status Not started Status Date 05-Jun-02     J
8 2.6.8 Final project release DUE 30-Sep-03
Description D6.7 Final project release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on final project release deliverables from middleware workpackages    
Dependency      
Status Not started Status Date 05-Jun-02     J
9 2.6.9 Final project release evaluation DUE 31-Dec-03
Description D6.8 Final evaluation of testbed operation
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on successful deployment of second project release    
Dependency      
Status Not started Status Date 05-Jun-02     J