3.1
1 3.1.1 Requirements, Architecture and Design Definition DUE 30-Jun-02
Description Document that establishes LHCb requirements for Grid based analysis and MC production.
Document establishes architecture constraints and leads to detailed design definition
 
Metric Document
 
Risk and/or None    
Dependency      
Status Not started Status Date   Modified Due Date   J
2 3.1.2 Prototype of Grid Interface DUE 30-Sep-02
Description Command line interface allows simple Gaudi analysis and Monte Carlo production jobs to be
submitted to EDG testbed sites. Job submission scripts automatically generated and some
error handling available.
Metric Demonstration of prototype for LHCb and ATLAS in the UK.
 
Risk and/or None    
Dependency      
Status Not started Status Date   Modified Due Date   J
3 3.1.3 Webpage mock GUI for feedback DUE 30-Sep-02
Description A simple web-page mock up of the GANGA GUI design to allow user feedback
 
 
Metric Creation of web-page mock GUI
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
4 3.1.4 Remote Grid Mass-Storage Write Capability DUE 30-Sep-02
Description Demonstration that the EDG RFIO from WP5 works in the LHCb context.
 
 
Metric Demonstration of basic functionality.
 
Risk and/or Depends on RFIO being produced by EDG WP5    
Dependency      
Status Not started Status Date   Modified Due Date   J
5 3.1.5 First GANGA Prototype DUE 31-Mar-03
Description GANGA prototype that includes user interaction regarding resource requests and the ability to
generate the JDL and an interface to MDS. Will also include monitoring tools and checkpointing.
 
Metric LHCb demonstration of defined functionality.
 
Risk and/or EDG WP1 and WP3 tools    
Dependency      
Status Not started Status Date   Modified Due Date   J
6 3.1.6 User-Controlled Site Configuration DUE 30-Sep-03
Description Development of syntax of a generic site configuration file.
 
 
Metric Demonstration of test Gaudi/Athena jobs running on Grid using standard conditions
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
7 3.1.7 Second GANGA Prototype DUE 31-Mar-04
Description GANGA prototype that includes GUI access to middleware and Gaudi/Athena services.
Functionality includes translation of meta-data into physical files; replica service to optimise location
of data; query facility to estimate resources; monitoring facilities for submitted jobs.
Metric Demonstration of prototype with specified functionality.
 
Risk and/or EDG WP1 WP2 WP3 services.    
Dependency      
Status Not started Status Date   Modified Due Date   J
8 3.1.8 Interface experiment Grid tools to GANGA DUE 30-Sep-04
Description Incorporated MC production system into GANGA supporting user-query of environment. Interface to
 experiment specific installation tools.
 
Metric Demonstration of prototype with specified functionality.
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
9 3.1.9 Final GANGA Version DUE 31-Dec-04
Description Document and demonstration of final GANGA product.
 
 
Metric Document and demonstration in LHCb and ATLAS contexts.
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J