7.1
1 7.1.1 Resource Deployment by Area DUE on going
Description The fraction of resources deployed according to current planning is a measure of effective
resource management
 
Metric Fraction deployed according to plan
 
 Current Total 100%        
Current Threshold 95%        
Status In Progress Status Date 05-Jun-02     J
2 7.1.2 Lost Effort DUE on going
Description Effort lost due to slow hiring is a measure of how effectively the resources are deployed.
 
 
Metric Number of lost man-months
 
 Current Total 12        
Current Threshold 6        
Status Not started Status Date 05-Jun-02     J
3 7.1.3 Hardware Delays DUE on going
Description Any delay in hardware purchases beyond planned schedule is a measure of how effectively
the process is managed.
 
Metric Number of months delay
 
 Current Total 0        
Current Threshold 2        
Status Not started Status Date 05-Jun-02     J
4 7.1.4 Travel Budget DUE on going
Description The match between the travel spend and the travel budget reflects on how well the travel budget
is managed.
 
Metric Travel overspend
 
 Current Total 0        
Current Threshold 0        
Status Not started Status Date 05-Jun-02     J