1.1.1 UK funding helps seed creation of LCG DUE 31-Dec-01
Description Commitment of substantial UK funding helps to seed the creation of a large-scale international
Grid project at CERN.
 
Metric Creation of project
 
Risk and/or Other countries will not provide funding.    
Dependency      
Status Complete Status Date 05-Jun-02 Modified Due Date   J
1.1.2 Cross membership of GridPP and LCG DUE 31-Mar-02
Description To ensure the close connection of GridPP and LCG cross-membership of the projects is required
at the highest levels.
 
Metric Establishment of cross-members on management bodies
 
Risk and/or      
Dependency      
Status Complete Status Date 05-Jun-02 Modified Due Date   J
1.1.3 LCG Plans DUE 01-Jul-02
Description LCG needs to develop a credible plan. UK should influence this if necessary.
 
 
Metric Planning information publicly available.
 
Risk and/or      
Dependency      
Status Complete Status Date 21-Jun-02 Modified Due Date   J See also http://lcg.web.cern.ch/LCG/PEB/Planning/default.htm
1.1.4 LHC experiments embrace LCG developments DUE 31-Dec-04
Description The ultimate metric for success is that the LHC experiments adopt substantial parts of the LCG  
product and that this is totally compatible with the developments in the UK.
 
Metric ATLAS, CMS, LHCb, (ALICE) use LCG product on UK grid. 
 
Risk and/or      
Dependency      
Status In Progress Status Date 05-Sep-02 Modified Due Date   J
1.1.5 Missing Effort DUE on going
Description Number of posts that are not presently filled
 
 
Metric Number of posts that are not presently filled
 
 Current Total 0  
Current Threshold -4  
Status Not started Status Date 01-Oct-02     J