1.4
1 1.4.1 Middleware Components Defined DUE 01-Dec-02 Corresponds to the subsequently definded LCG deliverable
Description As for applications environments, there are various competing sources of the different  1.3.2.8
Grid middleware components. A single set must be defined for LCG use.
 
Metric Single set of components defined.
 
Risk and/or It is hoped that GLUE will produce agreement on middleware    
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
2 1.4.2 Testing and Validation Process Defined DUE 01-Feb-03
Description Testing and Validation Process Defined
 
 
Metric Definition established
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J CLICK HERE AND THEN LOOK AT WG4 DOCUMENT Sec 2.3
3 1.4.3 Middleware Components Assembled, Tested and Available DUE 01-Apr-03
Description The middleware components identified in 1.3.1 are available in an agreed location for LCG, e.g.
the repository identified in 1.1.1
 
Metric Middleware Components Assembled, Tested and Available
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
4 1.4.4 Full Test Suite Completed DUE 01-Jun-03
Description Full Test Suite Completed
 
 
Metric Full Test Suite Completed
 
Risk and/or      
Dependency      
Status In Progress Status Date 09-Sep-02 Modified Due Date   J Tony Cass checking staus (email 3/Nov/03)
5 1.4.5 Future Milestones DUE 01-Sep-03
Description Milestones for the remainder of the LCG project are yet to be defined
 
 
Metric Milestones defined
 
Risk and/or      
Dependency       See new milestones below
Status Complete Status Date 22-Apr-03 Modified Due Date   J
6 1.4.6 Draft definition of Middleware to be used for LCG-3 service DUE 10-Dec-03
Description An initial definition of the middleware to be used for LCG-3 is available following discussions with
the participating sites.
This milestone corresponds to milestone 1.3.5.3 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
7 1.4.7 Final definition of Middleware to be used for LCG-3 service DUE 01-Mar-04
Description Th middleware to be used for the LCG-3 service has been agreed with all partners and the
definition has been published and agreed by SC2.
This milestone corresponds to milestone 1.3.5.5 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
8 1.4.8 Agreed LCG-3 middleware delivered for deployment DUE 01-Jun-04
Description The middleware of 1.4.7 is available in an agreed location ready for deployment on the
LCG-3 service.
This milestone corresponds to milestone 1.3.5.6 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
9 1.4.9 Updated PASTA Technology Review Complete DUE 01-Nov-04
Description The 2004 version of the PASTA reports has been published.
 
This milestone corresponds to milestone 1.3.4.4 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J