2.1
1 2.1.1 Deliver WP1 Effort DUE on going
Description Deliver WP1 effort as contracted
 
Primarily a UK responsibility
Metric Cumulative Effort Delivered
 
 Current Total 215.00%        
Current Threshold 90%        
Status In Progress Status Date 05-Jun-02     J
2 2.1.2 Install and Test DUE on going
Description Install and test EDG WP1 software
 
UK responsibility as part of an EDG-wide effort
Metric Latest WP1 software working in the UK
(Use 1 for 'yes' and 0 for 'no' in Current Total field below)
 Current Total 1        
Current Threshold 1        
Status In Progress Status Date 05-Jun-02     J
3 2.1.3 Technology Assessment DUE 31-Mar-01
Description D1.1 Report of current technology
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or          
Dependency          
Status Complete Status Date 05-Jun-02     J
4 2.1.4 Requirements & Architecture DUE 30-Jun-01
Description D1.2 Detailed report on requirements, architectural design, and evaluation criteria
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or          
Dependency          
Status Complete Status Date 05-Jun-02     J
5 2.1.5 First Project Release DUE 30-Sep-01
Description D1.3 Components and documentation for the first Project Release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
6 2.1.6 Co-allocation & Parallel Jobs DUE 30-Jun-02
Description D1.4 Co-allocation and parallel job partitioning architecture
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
7 2.1.7 Second Project release DUE 15-Jan-03
Description D1.5 Components and documentation for the second Project Release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 06-Jan-03     J
8 2.1.8 Final Project Release DUE 30-Sep-03
Description D1.6 Components and documentation for the final Project Release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
9 2.1.9 Evaluation DUE 31-Dec-03
Description D1.7 Final evaluation report
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on successful delivery of project releases    
Dependency      
Status Not started Status Date 05-Jun-02     J