2.4
1 2.4.1 Deliver WP4 Effort DUE on going
Description Deliver WP4 effort as contracted
 
Primarily a UK responsibility
Metric Cumulative Effort Delivered
 
 Current Total 256.30%  
Current Threshold 90%  
Status In Progress Status Date 05-Jun-02     J
2 2.4.2 Technology review DUE 30-Apr-01
Description D4.1 Report of current technology
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
3 2.4.3 Architecture DUE 30-Jun-01
Description D4.2 Architectural design report and evaluation criteria
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
4 2.4.4 First project release DUE 30-Sep-01
Description D4.3 Components and documentation for the first project release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
5 2.4.5 Second project release DUE 15-Jan-03
Description D4.4 Components and documentation for the second project release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or EDG may not stay with LCFG in the longer term    
Dependency      
Status Complete Status Date 06-Jan-03     J
6 2.4.6 Final project release DUE 30-Sep-03
Description D4.5 Components and documentation for the final project release
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or EDG may not stay with LCFG in the longer term    
Dependency      
Status Complete Status Date 05-Jun-02     J
7 2.4.7 Evaluation DUE 31-Dec-03
Description D4.6 Final evaluation report
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on successful delivery of project releases    
Dependency EDG may not stay with LCFG in the longer term    
Status Not started Status Date 05-Jun-02     J