2.5
1 2.5.1 Deliver WP5 Effort DUE on going
Description Deliver WP5 effort as contracted
 
Primarily a UK responsibility
Metric Cumulative Effort Delivered
 
 Current Total 135.90%  
Current Threshold 90%  
Status In Progress Status Date 05-Jun-02     J
2 2.5.2 Technology review DUE 31-Mar-01
Description D5.1 Report of current technology
 
Primarily a UK responsibility
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
3 2.5.3 Architecture DUE 30-Jun-01
Description D5.2 Detailed architectural design report and evaluation criteria
 
Primarily a UK responsibility
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
4 2.5.4 First Project release DUE 30-Sep-01
Description D5.3 Components and documentation for the first project release
 
Primarily a UK responsibility
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
5 2.5.5 Second Project release DUE 15-Jan-03
Description D5.4 Components and documentation for the second project release
 
Primarily a UK responsibility
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 06-Jan-03     J
6 2.5.6 Final Project release DUE 30-Sep-03
Description D5.5 Components and documentation for the third project release
 
Primarily a UK responsibility
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
7 2.5.7 Evaluation DUE 31-Dec-03
Description D5.6 Final evaluation report
 
Primarily a UK responsibility
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Depends on successful delivery of project releases    
Dependency      
Status Not started Status Date 05-Jun-02     J