2.7
1 2.7.1 Deliver WP7 Effort DUE on going
Description Deliver WP7 effort as contracted
 
Primarily a UK responsibility
Metric Cumulative Effort Delivered
 
 Current Total 186.70%  
Current Threshold 90%  
Status In Progress Status Date 05-Jun-02     J
2 2.7.2 Network infrastructure report DUE 30-Sep-01
Description D7.1 Report on network infrastructure for Testbed 1
 
Primarily a UK responsibility
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
3 2.7.3 Deploy monitoring DUE 31-Dec-01
Description D7.2 Demonstration and deployment of monitoring tools
 
Primarily done in the UK
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
4 2.7.4 Infrastructure & services DUE 30-Jun-02
Description D7.3 Intermediate report on network infrastructure and services
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
5 2.7.5 Final report DUE 31-Dec-03
Description D7.4 Final Report on network infrastructure and services
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Not Started Status Date 05-Jun-02     J
6 2.7.6 Interim security report DUE 31-Mar-02
Description D7.5 Security Report on first project release
 
Primarily a UK responsibility
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Complete Status Date 05-Jun-02     J
7 2.7.7 Security Design DUE 31-Jan-03
Description D7.6 Security Design report
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or Has input from core eScience project working with EDG    
Dependency      
Status Complete Status Date 07-Mar-03     J
8 2.7.8 Final Security report DUE 31-Dec-03
Description D7.7 Final security report
 
Not primarily a UK responsibility but UK will contribute
Metric Delivered on time and formally accepted by EDG
 
Risk and/or None    
Dependency      
Status Not started Status Date 05-Jun-02     J