3.1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1 |
3.1.1 |
Technology, Archtecture
and requirements documents |
DUE |
30-Sep-02 |
|
|
Description |
Review
of existing Monte Carlo production mechanisms in ATLAS and prototype
distributed |
|
|
production
systems. Establish architecture and design details of first prototype |
|
|
The
Atlas/LHCb GANGA review document should be used as a guide and an input. |
|
|
Metric |
Documents Produced |
|
|
|
|
|
Risk and/or |
Atlas/LHCb
GANGA review and requirements document |
|
|
|
|
Dependency |
|
|
|
|
There may be a revised document;
should check |
|
|
Status |
Complete |
Status Date |
17-Jan-03 |
Modified Due Date |
|
J |
|
http://www.gridpp.ac.uk/atlas/Projects/ATLASGridProjects.htm |
|
|
|
|
|
|
2 |
3.1.2 |
Installation Tool
Prototype development |
DUE |
31-Dec-02 |
|
|
Description |
The
CMT rpm generation will be tested and the pacman converter used to generate
cache files, |
|
|
and
pacman used to do remote installation. Non-advertised installation via the
sandbox and the SE |
|
|
will be
attempted and compared, inside and in addition to the DC1 context. |
|
|
Metric |
Tool Produced |
|
This has been demonstated but not
documented |
|
|
Not currently a GridPP responsibility but RHUL may become involved. |
|
The LCG adoption of SCRAM may cause
this to be |
|
|
Risk and/or |
Pacman
convertor |
|
|
|
dropped at this point. |
|
|
Dependency |
Rpm generation
facility in CMT |
|
|
|
See 3.1.6 below |
|
|
Status |
Complete |
Status Date |
17-Jan-03 |
Modified Due Date |
|
J |
|
|
|
|
|
|
3 |
3.1.3 |
First prototype of Grid
interface |
DUE |
31-Dec-02 |
|
3.1.3 |
First prototype of Grid
interface |
DUE |
31-Dec-02 |
|
Description |
A prototype
production system using the software intended for DC1 will be |
|
Click here for changeform |
Description |
A
prototype production system using the software intended for DC2 will be
produced based on |
|
produced
using EGD1 tools and a prototype GUI interface |
|
Old deliverable is here ---> |
the GANGA
prototype and GUI and the installation tool |
|
|
|
Modified because of EDG delays |
|
|
Metric |
Demonstration of prototype |
|
and realignment with LCG |
Metric |
Demonstration of prototype |
|
|
|
|
|
|
Risk and/or |
Full
chain available in Athena; GANGA prototype; Installation prototpe; |
3.1.2 |
|
|
|
Risk and/or |
Full
chain available in Athena; GANGA prototype; Installation prototpe; |
3.1.2 |
|
|
Dependency |
Replication
tools for bookkeeping files. |
|
|
|
Dependency |
Replication
tools for bookkeeping files. |
|
|
|
Status |
Complete |
Status Date |
07-Apr-03 |
Modified Due Date |
|
J |
|
Demo at CHEP'03 |
Status |
In Progress |
Status Date |
17-Jan-03 |
Modified Due Date |
|
J |
|
|
|
|
|
4 |
3.1.4 |
First release of
integrated MC production system |
DUE |
31-Dec-03 |
|
3.1.4 |
First release of
integrated MC production system |
DUE |
30-Jun-03 |
|
Description |
First
general release of Monte Carlo production system using LCG tools for DC2 |
|
Click here for changeform |
Description |
First
general release of Monte Carlo production system with integrated installation
tools for DC2 |
|
The
prototype - Monitoring of job
production and file replication. |
|
Click here for changeform2 |
The
prototype - Monitoring of job
production and file replication. |
|
- Templating or
virtual data methods for configuration |
|
Old deliverable is here ---> |
- Templating or
virtual data methods for configuration |
|
Metric |
Demonstration of prototype plus document |
|
Realigned with LCG |
Metric |
Demonstration of prototype plus document |
|
|
|
EDG delays |
|
|
Risk and/or |
GLUE and LCG
progress slower than planned. |
|
|
|
|
Risk and/or |
WP1 and WP3 monitoring
facilities |
|
|
|
Dependency |
|
|
|
|
Dependency |
|
|
|
|
Status |
In Progress |
Status Date |
07-Apr-03 |
Modified Due Date |
|
J |
|
Status |
In Progress |
Status Date |
17-Jan-03 |
Modified Due Date |
|
J |
|
|
|
|
|
5 |
3.1.5 |
Data Challenge 1 |
DUE |
31-Mar-03 |
|
3.1.5 |
Revised Installation Tool
design document |
DUE |
30-Jun-03 |
|
Description |
Several 10's
of millions of events will be simulated, reconstructed and analaysed using
the EDG |
|
Click here for changeform |
Description |
In
the light of the report on the prototype and external developments, the
architecture of the |
|
1.x release
and other grid tools for a significant portion of the work. A report will
review the early |
|
Old deliverable is here ---> |
Installation
Tools will be revised. |
|
experiences with DC1 |
|
New deliverable is
combination |
|
|
Metric |
Several 10's of millions of events produced; EDG Grid tools tested |
|
of two DC1 deliverables in |
Metric |
Document |
|
Report. |
|
original submission. |
|
|
Risk and/or |
|
|
|
|
Click here for link. |
Risk and/or |
Prototype
released on time |
3.1.3 |
|
|
Dependency |
|
|
|
|
Dependency |
|
|
|
|
Status |
Complete |
Status Date |
17-Jan-03 |
Modified Due Date |
|
J |
|
Status |
Not started |
Status Date |
|
Modified Due Date |
|
J |
|
|
|
6 |
3.1.6 |
Installation with
publication |
DUE |
31-Dec-03 |
|
|
Description |
The
integration of installation tool with MDS/Grid publication of environment
setting, |
|
Click here for changeform |
|
|
Grid inquiry
for environment detection. |
|
Click here for changeform2 |
|
|
|
|
Deliverable deleted because |
|
|
Metric |
Demonstration of tool. |
|
LCG chose SCRAM |
|
|
|
|
Deliverable then reinstated because |
|
|
Risk and/or |
WP3
publication services. EDG installation procedures. |
|
|
|
ATLAS decided to continue with CMT |
|
|
Dependency |
|
|
|
|
|
|
|
Status |
Not started |
Status Date |
|
Modified Due Date |
|
J |
|
|
|
|
7 |
3.1.7 |
Prototype of revised
production tool |
DUE |
31-Dec-03 |
|
|
Description |
Implementation
of the new architecture |
|
|
|
|
|
|
|
|
Metric |
Report and demonstration |
|
|
|
|
|
Risk and/or |
|
|
|
|
|
Dependency |
|
|
|
|
|
Status |
Not started |
Status Date |
|
Modified Due Date |
|
J |
|
|
|
|
8 |
3.1.8 |
Monte Carlo production
with expanded functionality. |
DUE |
31-Mar-04 |
|
|
Description |
Integration
with the corresponding GANGA development. Integration with the revised
installation tool |
|
|
|
|
|
|
|
|
Metric |
Document and demonstration |
|
|
|
|
|
Risk and/or |
EDG testbed
services. GANGA expanded functionality release. |
|
|
|
|
Dependency |
|
|
|
|
|
Status |
Not started |
Status Date |
|
Modified Due Date |
|
J |
|
|
|
|
9 |
3.1.9 |
Data Challenge 2 |
DUE |
30-Sep-04 |
|
Click her for first changeform |
3.1.9 |
Final Installation Tool
Version |
DUE |
30-Jun-04 |
|
Description |
Seveal 100
million events will be generated, simulated, reconstructed and analysed using
LCG2 |
|
Click her for second changeform |
Description |
Document
describing Installation Tool and public demonstration. |
|
release
(plus interface to US and NorduGrid). The experience with DC2 will be
reviewed and future |
|
Click her for third changeform |
|
|
requirements
determined |
|
Click her for fourth changeform |
|
|
Metric |
Several 100 million events generated |
|
Original deliverable is here ---> |
Metric |
Document and demonstration |
|
Report |
|
New deliverable is
combination |
|
|
Risk and/or |
LCG releases
needed on time |
|
|
|
of two DC1 deliverables in |
Risk and/or |
|
|
|
|
Dependency |
|
|
|
|
original submission. |
Dependency |
|
|
|
|
Status |
Not started |
Status Date |
|
Modified Due Date |
|
J |
|
2nd-4th changes re-align with LCG |
Status |
Not started |
Status Date |
|
Modified Due Date |
|
J |
|
|
|
Click here for link. |
|
# |
3.1.10 |
Final Monte Carlo
Production System Version |
DUE |
31-Dec-04 |
|
|
Description |
Document
describing Monte Carlo production system and public demonstration. |
|
|
|
|
|
|
|
|
Metric |
Document and demonstration |
|
|
|
|
|
Risk and/or |
|
|
|
|
|
Dependency |
|
|
|
|
|
Status |
Not started |
Status Date |
|
Modified Due Date |
|
J |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|