3.1
1 3.1.1 Technology, Archtecture and requirements documents DUE 30-Sep-02
Description Review of existing Monte Carlo production mechanisms in ATLAS and prototype distributed  
production systems. Establish architecture and design details of first prototype
The Atlas/LHCb GANGA review document should be used as a guide and an input.
Metric Documents Produced
 
Risk and/or Atlas/LHCb GANGA review and requirements document    
Dependency       There may be a revised document; should check
Status Complete Status Date 17-Jan-03 Modified Due Date   J http://www.gridpp.ac.uk/atlas/Projects/ATLASGridProjects.htm
2 3.1.2 Installation Tool Prototype development DUE 31-Dec-02
Description The CMT rpm generation will be tested and the pacman converter used to generate cache files, 
and pacman used to do remote installation. Non-advertised installation via the sandbox and the SE 
will be attempted and compared, inside and in addition to the DC1 context.
Metric Tool Produced This has been demonstated but not documented
Not currently a GridPP responsibility but RHUL may become involved. The LCG adoption of SCRAM may cause this to be
Risk and/or Pacman convertor     dropped at this point.
Dependency Rpm generation facility in CMT     See 3.1.6 below
Status Complete Status Date 17-Jan-03 Modified Due Date   J
3 3.1.3 First prototype of Grid interface DUE 31-Dec-02 3.1.3 First prototype of Grid interface DUE 31-Dec-02
Description A prototype production system using the software intended for DC1 will be Click here for changeform Description A prototype production system using the software intended for DC2 will be produced based on 
produced using EGD1 tools and a prototype GUI interface  Old deliverable is here ---> the GANGA prototype and GUI and the installation tool
  Modified because of EDG delays  
Metric Demonstration of prototype and realignment with LCG Metric Demonstration of prototype
     
Risk and/or Full chain available in Athena; GANGA prototype; Installation prototpe;  3.1.2     Risk and/or Full chain available in Athena; GANGA prototype; Installation prototpe;  3.1.2  
Dependency Replication tools for bookkeeping files.     Dependency Replication tools for bookkeeping files.    
Status Complete Status Date 07-Apr-03 Modified Due Date   J Demo at CHEP'03 Status In Progress Status Date 17-Jan-03 Modified Due Date   J
4 3.1.4 First release of integrated MC production system DUE 31-Dec-03 3.1.4 First release of integrated MC production system DUE 30-Jun-03
Description First general release of Monte Carlo production system using LCG tools for DC2  Click here for changeform Description First general release of Monte Carlo production system with integrated installation tools for DC2
The prototype  - Monitoring of job production and file replication. Click here for changeform2 The prototype  - Monitoring of job production and file replication.
                        - Templating or virtual data methods for configuration Old deliverable is here --->                         - Templating or virtual data methods for configuration
Metric Demonstration of prototype plus document Realigned with LCG Metric Demonstration of prototype plus document
  EDG delays  
Risk and/or GLUE and LCG progress slower than planned.       Risk and/or WP1 and WP3 monitoring facilities     
Dependency       Dependency      
Status In Progress Status Date 07-Apr-03 Modified Due Date   J Status In Progress Status Date 17-Jan-03 Modified Due Date   J
5 3.1.5 Data Challenge 1 DUE 31-Mar-03 3.1.5 Revised Installation Tool design document DUE 30-Jun-03
Description Several 10's of millions of events will be simulated, reconstructed and analaysed using the EDG Click here for changeform Description In the light of the report on the prototype and external developments, the architecture of the 
1.x release and other grid tools for a significant portion of the work. A report will review the early Old deliverable is here ---> Installation Tools will be revised.
 experiences with DC1  New deliverable is combination   
Metric Several 10's of millions of events produced; EDG Grid tools tested of two DC1 deliverables in Metric Document
Report. original submission.  
Risk and/or       Click here for link. Risk and/or Prototype released on time 3.1.3  
Dependency       Dependency      
Status Complete Status Date 17-Jan-03 Modified Due Date   J Status Not started Status Date   Modified Due Date   J
6 3.1.6 Installation with publication DUE 31-Dec-03
Description The integration of installation tool with MDS/Grid publication of environment setting, Click here for changeform
Grid inquiry for environment detection. Click here for changeform2
  Deliverable deleted because
Metric Demonstration of tool. LCG chose SCRAM
  Deliverable then reinstated because
Risk and/or WP3 publication services. EDG installation procedures.     ATLAS decided to continue with CMT
Dependency        
Status Not started Status Date   Modified Due Date   J
7 3.1.7 Prototype of revised production tool DUE 31-Dec-03
Description Implementation of the new architecture
 
 
Metric Report and demonstration
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
8 3.1.8 Monte Carlo production with expanded functionality. DUE 31-Mar-04
Description Integration with the corresponding GANGA development. Integration with the revised installation tool
 
 
Metric Document and demonstration
 
Risk and/or EDG testbed services. GANGA expanded functionality release.    
Dependency      
Status Not started Status Date   Modified Due Date   J
9 3.1.9 Data Challenge 2 DUE 30-Sep-04 Click her for first changeform 3.1.9 Final Installation Tool Version DUE 30-Jun-04
Description Seveal 100 million events will be generated, simulated, reconstructed and analysed using LCG2 Click her for second changeform Description Document describing Installation Tool and public demonstration.
release (plus interface to US and NorduGrid). The experience with DC2 will be reviewed and future Click her for third changeform  
requirements determined Click her for fourth changeform  
Metric Several 100 million events generated Original deliverable is here ---> Metric Document and demonstration
Report New deliverable is combination   
Risk and/or LCG releases needed on time     of two DC1 deliverables in Risk and/or      
Dependency       original submission. Dependency      
Status Not started Status Date   Modified Due Date   J 2nd-4th changes re-align with LCG Status Not started Status Date   Modified Due Date   J
Click here for link.
# 3.1.10 Final Monte Carlo Production System Version DUE 31-Dec-04
Description Document describing Monte Carlo production system and public demonstration.
 
 
Metric Document and demonstration
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J