3.5
1 3.5.1 Preliminary Replica Catalog System DUE 30-Sep-02
Description Design and implement a preliminary system that will provide each site with the location(s) of every
data file by adding one byte per file per site to the existing mySQL system
 
Metric Tool is demonstrated
 
Risk and/or      
Dependency      
Status Complete Status Date 13-Jan-03 Modified Due Date   J This is the skimData referred to in this talk
2 3.5.2 Prototype Job Creator and Submitter DUE 31-Dec-02
Description Use the BaBar Preliminary Replica catalog system and the EDG resource broker to implement.
Creater produces jobs with data grouped according to availability at sites. Submitter (RB) receives
jobs with site specfied so has little flexibility at this point.
Metric Tool is demonstated
 
Risk and/or Replica catalogue system 3.5.1  
Dependency EDG Resource Broker (stable in current release).    
Status Complete Status Date 13-Jan-03 Modified Due Date   J This is the submitter referred to in this talk
3 3.5.3 Assessment Document DUE 30-Jun-03
Description Produce an assessment of the BaBarGrid system as it currently exists, including actual
experience and progress being made with the EDG system.
 
Metric Document available
 
Risk and/or Prototype Job Creator and Submitter 3.5.2  
Dependency      
Status Complete Status Date   Modified Due Date   J Waiting for Link from RB
4 3.5.4 Production BaBarGrid DUE 31-Dec-03
Description A production version of the previous tools 3.4.1 and 3.4.2 enabling BaBar users to run 
jobs on any available data without specifying the site(s) to be used, and to retrieve merged output.
 
Metric Grid available for UK users.
 
Risk and/or Replica catalog 3.5.1  
Dependency Job submitter 3.5.2  
Status In Progress Status Date   Modified Due Date   J
5 3.5.5 Assessment of Production System DUE 30-Jun-04
Description Assessment of the production system, including its popularity with BaBar users
 
 
Metric Document Produced
 
Risk and/or Production BaBarGrid 3.5.4  
Dependency      
Status Not started Status Date   Modified Due Date   J
6 3.5.6 Final BaBar System DUE 31-Dec-04
Description Tune, document and optimse the production system
 
 
Metric Document describing system
 
Risk and/or Production Grid 3.5.4  
Dependency Assessment document 3.5.5  
Status Not started Status Date   Modified Due Date   J
7 3.5.7 Persistent Data Policy DUE 31-Mar-03 Click her for changeform
Description Assess the requirements for persistent data in BaBarGrid in the light of the revised BaBar  BaBar computing model was not presented in Sep
computing model as planned but was delayed to December.
 
Metric Document available
  Roger to put report on web. Email 28/4/03
Risk and/or BaBar computing model report (due Sep 2002)    
Dependency      
Status Complete Status Date 13-Jan-03 Original Due Date 31-Dec-02 J