3.6
1 3.6.1 Architecture Design and Technology Review DUE 30-Jun-02
Description Document describing architecture to be used for the upgrade of SAM
Document reviewing current technology
 
Metric Documents produced
 
Risk and/or None   D0
Dependency      
Status Complete Status Date   Modified Due Date   J
2 3.6.2 Prototype CDF-SAM Interface DUE 30-Jun-02
Description A preliminary interface between the CDF analysis framework and SAM including a GUI for large
scale declaration of data-sets to SAM and an interface to the SAM data retrieval system.
 
Metric Demonstration of functionality on UK site.
  Working CDF SAM stations at Glasgow/UCL etc.
Risk and/or None   CDF
Dependency      
Status Complete Status Date   Modified Due Date   J
3 3.6.3 Phase-1 SAM Development DUE 30-Sep-02
Description SAM modified to include GridFTP transport option; Condor-G job submission to a hand-chosen
remote site; monitoring information services.
 
Metric Demonstration of functionality
 
Risk and/or May be problems with interface to GSI.    D0
Dependency Depends on Condor-g deployment.    
Status Complete Status Date 13-Jan-03 Modified Due Date   J
4 3.6.4 Final CDF-SAM interface DUE 31-Dec-02
Description Based upon prototype results, final design will be implemented.
 
 
Metric Demonstration of interface on UK site.
 
Risk and/or Depends on prototype. 3.6.2 CDF
Dependency      
Status Complete Status Date 17-Jan-03 Modified Due Date   J
5 3.6.5 CDF Monte Carlo Production as a SAM Task. DUE 01-Oct-03
Description Extend CDF use of SAM from simple file retrieval to fully integrated Monte Carlo production. Click here for changeform
  Re-prioritorized according to CDF
  plans. The 3.6.7 deliverable has been 
Metric Demonstration of CDF Monte Carlo production using SAM in the UK bought forward and this one delayed.
   
Risk and/or Depends on completion of related work within the CDF collaboration to    CDF  
Dependency allow communication with various databases (geometry, calibration, etc).    
Status In Progress Status Date 13-Jan-03 Modified Due Date   J
6 3.6.6 Prototype SAM Monte Carlo Production system using Resource Broker DUE 31-Mar-03
Description Extension of SAM functionality to include use of resource broker. Will also include monitoring
services and request interface.
 
Metric Demonstration of SAM prototype with specified functionality in the UK.
 
Risk and/or Depends on D0 architecture definition 3.6.1 D0
Dependency and development of associated areas within D0    
Status Complete Status Date 23-Apr-03 Modified Due Date   J See this link also…
7 3.6.7 Demonstration of CDF/SAM jobs moving to data. DUE 31-Mar-03
Description Adaptation of SAM to move jobs to data as an option needs to be integrated into CDF framework.
 
 
Metric Demonstration of CDF/SAM jobs moving to data in the UK.
 
Risk and/or Depends on development of this SAM functionality by the core SAM team.   CDF
Dependency and the SAM Grid team    
Status Complete Status Date 17-Jan-03 Modified Due Date   J Link to GridPP web page news item
8 3.6.8 Report on first year SAM/CDF Progress DUE 30-Jun-03
Description A brief summary document that describes progress in the first year and highlights problems and
issues. This will be used to set/modify targets for the remainder of the project.
 
Metric Document produced
 
Risk and/or None   CDF
Dependency      
Status Complete Status Date   Modified Due Date   J NEED THIS LINK
9 3.6.9 Pilot SAM Grid for D0 users. DUE 01-Dec-03
Description Documentation and demonstration of a limited D0-grid based on SAM capable of providing a service Click here for changeform
to 'intelligent users' in the UK. Functionality includes automated submission of Monte Carlo and Delayed by 2 months due to a change 
analysis jobs. in priorities within D0
Metric Documented demonstration.  
   
Risk and/or Depends on much associated work with core SAM team and D0   D0  
Dependency collaboration.    
Status Not started Status Date   Modified Due Date   J
# 3.6.10 Demonstration of SAM as a Data Handling System for CDF DUE 31-Dec-03
Description Deliver SAM for use on CDF's central analysis facility as the data handling system.
 
 
Metric Demonstration of SAM for data handling in UK and Fermilab
 
Risk and/or Depends on formal adoption of SAM by CDF   CDF
Dependency Provision of sufficient CDF manpower    
Status Complete Status Date   Modified Due Date   J According to Q9 report; awaiting confirmation
# 3.6.11 Robust SAM-based grid service for D0 DUE 30-Sep-04
Description Demonstration and documentation of a robust SAM-based service for significant D0 physics Click here for changeform
production tasks suitable for use by general collaboration members. Delayed by 6 months due to a change 
  in priorities within D0
Metric Documented demonstration  
   
Risk and/or Depends on development of SAM and D0 software and by formal   D0  
Dependency acceptance by the D0 collaboration.    
Status Not started Status Date   Modified Due Date   J
# 3.6.12 Final Report on SAM/CDF integration DUE 31-Dec-04
Description A document on the final product for CDF. Issues addressed include the technical success of the
integration of SAM and the degree to which CDF has adopted this for data handling.
 
Metric Document
 
Risk and/or     CDF
Dependency       May change this to a milestone 9 months earlier that specifies
Status Not started Status Date   Modified Due Date   J work required in last 9 months.