3.8
1 3.8.1 One non-funded application has used UK testbed DUE 30-Sep-02
Description  
 
 
Metric One non-funded application has used UK testbed
 
Risk and/or      
Dependency      
Status Complete Status Date   Modified Due Date   J LISA jobs were run
2 3.8.2 Two non-funded application have used testbed DUE 30-Sep-03
Description  
 
 
Metric Two non-funded application have used testbed
 
Risk and/or      
Dependency      
Status Complete Status Date   Modified Due Date   J MICE jobs were run: See Page-14 of the link
3 3.8.3 Significant bids for resources by non-funded applications DUE 31-Dec-04
Description There are significant bids for GridPP resources from applications that were not directly funded by 
the GridPP programme.
 
Metric Amount of resources requested by non-funded applications
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J