4.2
1 4.2.1 2002 Tier-1 hardware commissioned  DUE 01-Oct-02
Description Hardware installed and demonstrated to meet tender specifications
300 CPUs and 40TB of disk shared with BaBar.
 
Metric Purchase accepted
Hardware available for use.
Risk and/or       312 CPU (156 dual) installed
Dependency       Link to final version of JG OC document
Status Complete Status Date 10-Sep-02 Modified Due Date   J Some concern about some disks but issue resolved with vendor.
2 4.2.2 Tier-1 Centre used. DUE 31-Dec-02
Description Hardware should meet the needs (as far as possible) of the LHC experiments Due to the quantized nature of the data Challenges this was not
  quite completed according to the due date or to the metric, but, 
  from January to May 2003 the LHC experiments used 77% of their
Metric LHC experiments use more than 80% of hardware nominally reserved for their use for  resource allocation (nominally 30% of the hardware)
substantial periods. See this link
Risk and/or       and this link
Dependency      
Status Complete Status Date 08-May-03 Modified Due Date   J
3 4.2.3 2003 Tier-1 hardware commissioned  DUE 01-Oct-03
Description Hardware installed and demonstrated to meet tender specifications
 
 
Metric Purchase accepted
Hardware available for use.
Risk and/or      
Dependency      
Status Complete Status Date   Modified Due Date   J
4 4.2.4 Tier-1 Centre used. DUE 31-Dec-03
Description Hardware should meet the needs (as far as possible) of the LHC experiments
 
 
Metric LHC experiments use more than 80% of hardware nominally reserved for their use.
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
5 4.2.5 2004 Tier-1 hardware commissioned  DUE 01-Oct-04
Description Hardware installed and demonstrated to meet tender specifications
 
 
Metric Purchase accepted
Hardware available for use.
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
6 4.2.6 Tier-1 Centre used. DUE 31-Dec-04
Description Hardware should meet the needs (as far as possible) of the LHC experiments
 
 
Metric LHC experiments use more than 80% of hardware nominally reserved for their use.
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
7 4.2.7 Tier-1 Centre meets target size. DUE 31-Dec-04
Description Tier-1 Centre meets target size.
 
 
Metric Expect 2000 nodes and 500TB in the UK. Approximately 50% in Tier-1.
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J