7.1
1 7.1.1 Resource Deployment by Area DUE on going
Description The fraction of resources deployed according to current planning is a measure of effective
resource management
 
Metric Fraction deployed according to plan
 
 Current Total 96%   Underspend of £0.09m at RAL in FY02
Current Threshold 95%  
Status In Progress Status Date 05-Jun-02     J
2 7.1.2 Missing Effort DUE on going
Description Number of posts that are not presently filled
 
 
Metric Number of posts that are not presently filled
 
 Current Total -1  
Current Threshold -2   CDF post at Glasgow
Status Not started Status Date 01-Oct-02     J
3 7.1.3 Hardware Delays DUE on going
Description Any delay in hardware purchases beyond planned schedule is a measure of how effectively
the process is managed.
 
Metric Number of months delay
 
 Current Total -3  
Current Threshold -3  
Status Not started Status Date 05-Jun-02     J
4 7.1.4 Travel Budget DUE on going
Description The match between the travel spend and the travel budget reflects on how well the travel budget
is managed.
 
Metric Travel overspend(£K)
(Overspend entered as negative number; underspend as positive number)
 Current Total 37 Only really known  at end of FY so we will enter 
Current Threshold -5 projected overspend given current information
Status Not started Status Date 05-Jun-02     J