| 7.2 | |||||||||||||
| 1 | 7.2.1 | Monitoring Mechanism | DUE | 01-May-02 | |||||||||
| Description | An easy to use mechanism for monitoring effort in the project on a quarterly basis is required | ||||||||||||
| Metric | Development of Mechanism | ||||||||||||
| Risk and/or | |||||||||||||
| Dependency | See next deliverable | ||||||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | |||||||||
| 2 | 7.2.2 | Monitoring Implementation | DUE | 15-Oct-02 | |||||||||
| Description | The monitoring mechanism needs to be implemented and run. | ||||||||||||
| Metric | First full run of monitoring mechanism completed. | ||||||||||||
| Risk and/or | |||||||||||||
| Dependency | |||||||||||||
| Status | Complete | Status Date | 01-Oct-01 | J | |||||||||
| 3 | 7.2.3 | Monitoring information processing | DUE | 15-Dec-02 | |||||||||
| Description | A semi-automated mechanism for processing the monitoring information needs to be developed | ||||||||||||
| Link to OC resource report May03 that has tables | |||||||||||||
| for both EDG and Applications that are generated | |||||||||||||
| Metric | Development of processing system | from this processing system | |||||||||||
| Risk and/or | |||||||||||||
| Dependency | |||||||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | |||||||||