1.5
1 1.5.1 Complete Specification of LCG-1 DUE 24-Nov-02
Description Agreement is reached on the level of resources required for LCG-1 and how these are to be 
distributed across at least 5 sites in 3 continents.
 
Metric Specification available
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J CLICK HERE AND SEE WG2 DOCUMENT
2 1.5.2 Institutes Fabric Ready to Install DUE 15-May-03 Click here for changeform  
Description Acquisition and installation of agreed hardware. Date changed to match subsequently
  defined LCG milestone
   
Metric The institutes identified in 1.5.1 have completed the acquisition and installation of the agreed  
hardware.  
Risk and/or      
Dependency      
Status Complete Status Date 16-Apr-03 Modified Due Date   J (See LCG Resource slide in the link)
3 1.5.3 Certification Started DUE 30-May-03 Click here for changeform  
Description   Date changed to match subsequently
Installation of agreed middleware (1.5.1) on hardware of 1.5.2. defined LCG milestone ~1.4.1.4 (4.356)
   
Metric Certification Started  
   
Risk and/or   1.4.1  
Dependency   1.5.2  
Status Complete Status Date 16-Apr-03 Modified Due Date   J (For LCG-1 status, click dots on map on LCG home page)
4 1.5.4 Certification and LCG-1 Build and Delivery complete DUE 30-Jun-03 Click here for changeform  
Description   Date changed to match subsequently
All the agreed hardware and software is up and running at each individual LCG-1 site. defined LCG milestone ~1.4.1.6 (4.956)
   
Metric Certification and LCG-1 Build and Delivery complete  
   
Risk and/or      
Dependency      
Status Complete Status Date 16-Apr-03 Modified Due Date   J See Link for 1.5.3 completion
5 1.5.5 Commissioning Started DUE 30-Jun-03 Click here for changeform  
Description This is the start of the process to bring the different sites together to form a coherent LCG-1. Date changed to match subsequently
  defined LCG milestone ~1.4.1.6 (4.956)
   
Metric Commissioning Started  
 
Risk and/or      
Dependency      
Status Complete Status Date 16-Apr-03 Modified Due Date   J See email from TC on 3/Nov/03
6 1.5.6 Commissioning Completed DUE 24-Nov-03
Description   Click here for changeform  
  Date changed to match subsequently
  defined LCG milestone 1.4.1.7 (4.358)
Metric The application software of 1.2.4 runs successfully on the LCG-1 service.  
   
Risk and/or   1.2.4  
Dependency      
Status Not started Status Date 16-Apr-03 Modified Due Date   J
7 1.5.7 Future Milestones DUE 01-Sep-03
Description Milestones for the remainder of the LCG project are yet to be defined
 
 
Metric Milestones defined
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J See new milestones below
8 1.5.8 LCG-3 Service Defined DUE 27-Feb-04
Description The LCG-3 service is defined in terms of sites involved, hardware available and performance
criteria. 
This milestone corresponds to milestone 1.4.4 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
9 1.5.9 LCG-3 Pilot Available DUE 01-Jul-04
Description An initial LCG-3 service is available in accordance with the plans of 1.5.8.
 
This milestone corresponds to milestone 1.4.12.1 of the LCG plan.
Metric  
 
Risk and/or   1.4.8  
Dependency   1.5.8  
Status Not started Status Date   Modified Due Date   J
# 1.5.10 LCG-3 Fulfills Performance Goals DUE 17-Dec-04
Description The LCG-3 service meets the performance goals set in the initial service definition (1.5.8).
 
This milestone corresponds to milestone 1.4.13 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J